Return to Agency Capital Project Detail
Department of Fish and Wildlife
Owned Facilities by County - 1997-99
Project Map



Capital Overview


The Department of Fish and Wildlife is charged with preserving, protecting, and perpetuating Washington's diverse fish, shellfish, and wildlife resources and their habitats for the benefit of Washington's citizens. In addition, the federal courts have charged the state with ensuring that treaty tribes have an opportunity to catch their share of harvestable fish and shellfish resources.

The Department owns or manages for other governmental entities over 850,000 acres of land statewide. These holdings include 77 fish hatcheries, rearing and spawning sites, and numerous fish passage and collection facilities, 610 public fishing and access sites, and shellfish and wildlife reserves open to recreation. The agency operates pheasant rearing farms and has several administrative offices. Maintaining various lands and facilities presents unique capital challenges as a result of exposure to natural conditions, effects of fire and flooding, and constant public use.

The focus of the Department's capital budget continues to be one of health and safety compliance, habitat conservation and restoration to maintain healthy natural fish and wildlife populations, and enhancement of those populations for recreational and commercial benefit.


Capital Plan Highlights



1997-99 Agency Detail
Department of Fish and Wildlife
98-1-001
Minor Works - Preservation
This project provides funding for modifications to agency facilities and infrastructure.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
3,208,887 1,776,236 757,181 1,293,000 6,000,000 13,035,304
Funds: General Fund - Federal 2,000,001
State Building Construction Account - State 11,035,303
98-1-002
Underground Storage Tank Removal/Replacement
This project provides funding for removal or replacement of underground storage tanks to reduce environmental risks.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,299,000 2,338,000 596,185 200,000 4,433,185
Funds: State Building Construction Account - State 4,433,185
98-1-003
Emergency Repairs
This appropriation will serves as a contigency fund to provide for work of an unanticipated nature at agency facilities. Emergency projects typically result from fire, flood, wind, snow damage or general public vandalism or misuse.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,100,000 430,646 219,353 300,000 1,200,000 3,249,999
Funds: State Building Construction Account - State 3,249,999
98-1-004
Dam Inspection/Repair
The agency owns 54 earthen dams and most are in need of repair. The operating budget includes funding to implement an inspection program and begin maintenance work. This project provides funding to undertake the most critical repairs identified through the inspection program.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
300,000 300,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 06-30-99 40,000
Construction 07-01-97 / 06-30-99 460,000
Funds: State Building Construction Account - State 300,000
98-1-005
Facilities Renovation
This project provides funding for specific renovations including reroofing, facility renovation, resurfacing parking areas, and repair or replacement of building and infrastructure systems.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
3,056,300 697,382 302,618 1,015,000 4,000,000 9,071,300
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 04-30-99 100,000
Construction 07-01-97 / 06-30-99 915,000
Funds: State Building Construction Account - State 9,071,300
98-1-006
Hatchery Renovation
This project provides funding for improvements and renovations at state operated hatcheries. Work includes renovating or replacing hatchery buildings, storage buildings, reroofing, improving water supply systems, and installation of pathogen-free water incubation systems.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
4,826,155 2,293,798 906,202 3,025,000 9,000,000 20,051,155
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 04-30-99 300,000
Construction 07-01-97 / 06-30-99 2,725,000
Funds: State Building Construction Account - State 20,051,155
98-1-007
Recreational Access Redevelopment
This project provides funding to replace boat launch ramps, toilet facilities, and viewing areas, to upgrade parking areas and replace fencing. The agency maintains and operates 610 public fishing and access sites located on various lakes, streams, and saltwater shores.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,741,629 818,221 119,300 912,000 4,200,000 8,791,150
Phase Start Date / End Date Phase Cost
Construction 07-01-97 / 06-30-99 912,000
Funds: General Fund - Federal 4,110,000
State Building Construction Account - State 1,752,005
Outdoor Recreation Account - State 1,481,982
Wildlife Account - Federal 1,447,163
98-1-008
Voights Creek Hatchery Adult Pond Renovation
This project renovates the adult pond, isolates pollution abatement drainage from the pond, allows adequate pond cleaning, and expands facilities to handle large numbers of returning fish. This work will bring the facility into compliance with national pollution discharge standards.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,400,000 1,400,000
Phase Start Date / End Date Phase Cost
Design 05-01-97 / 04-01-98 119,000
Construction 04-01-98 / 12-31-98 1,281,000
Funds: State Building Construction Account - State 1,400,000
98-1-009
Coast/Puget Sound Wild Salmonid Habitat Restoration
This project restores habitat and improves fish access by constructing in-stream structures, natural rearing ponds, off channel spawning/rearing areas, and fishways at impassable road culverts, dams, and falls.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
5,170,000 3,816,230 1,428,770 5,100,000 22,400,000 37,915,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 06-30-99 400,000
Construction 07-01-97 / 06-30-99 4,700,000
Funds: General Fund - Federal 4,800,000
General Fund - Private/Local 4,800,000
State Building Construction Account - State 28,315,000
98-1-010
Coast/Puget Sound Wildstock Restoration/Hatcheries
This project modifies existing hatchery or fish passage facilities to support at-risk stock rehabilitation efforts, develop remote culture capabilities for specific restoration programs, and develop captive brood stock capability for stock restorations.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
3,280,000 1,985,814 814,186 1,000,000 4,000,000 11,080,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 06-30-99 100,000
Construction 07-01-97 / 06-30-99 900,000
Funds: General Fund - Federal 2,000,000
State Building Construction Account - State 9,080,000
98-1-011
Fish Protection Facilities
This project allows the agency to continue improving fish screening facilities at various water diversion locations to protect wild stock. Work will be concentrated in the Methow and Okanogan basins.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,656,000 644,765 1,654,335 700,000 7,400,000 13,055,100
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 06-30-99 100,000
Construction 07-01-97 / 06-30-99 1,800,000
Funds: General Fund - Federal 7,875,000
General Fund - Private/Local 1,000,000
State Building Construction Account - State 4,180,100
98-1-012
Statewide Fencing Renovation/Construction
This project improves or maintains boundary fencing, crop protection fencing, and eight foot high big game drift fencing. Construction, maintenance and renovation of fences is necessary to prevent domestic livestock from encroaching on state wildlife areas and to prevent wildlife from damaging agricultural crops.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,875,000 475,800 272,743 570,000 2,400,000 5,593,543
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 04-30-99 60,000
Construction 07-01-97 / 06-30-99 510,000
Funds: State Building Construction Account - State 5,593,543
98-1-013
Wildlife Area Renovation
This project improves roads, public access areas, habitat plots, fencing, irrigation systems, buildings, and other structures on the 800,000 acres of wildlife lands owned or managed by the department.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
839,000 386,196 238,804 548,000 2,200,000 4,212,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 04-30-99 48,000
Construction 07-01-97 / 06-30-99 500,000
Funds: Wildlife Account - State 4,212,000
98-2-002
Crop/Orchard Protection Fencing
This project provides fencing materials for land owners who are responsible for installation and maintenance of wild game fences to protect orchards and crops.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
300,000 1,200,000 1,500,000
Phase Start Date / End Date Phase Cost
Construction 07-01-97 / 06-30-98 300,000
Funds: State Building Construction Account - State 1,500,000
98-2-005
Game Farm Consolidation
This project continues collocation efforts to consolidate game bird farms into one location in Lewis County.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,125,000 468,530 231,470 300,000 2,125,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 04-30-98 15,000
Construction 02-01-98 / 06-30-99 285,000
Funds: Wildlife Account - State 2,125,000
98-2-006
Warm Water Game Fish Access Facilities
This project provides funding for accesses, piers, parking, restrooms and other usage related projects at fishing areas supporting bass, channel catfish, walleye, crappie and/or tiger musky. Funding is also provided through a license surcharge on warm water fisheries.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
560,000 2,240,000 2,800,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 02-01-99 47,600
Construction 04-01-98 / 06-30-99 512,400
Funds: Warm Water Game Fish Account - State 2,800,000
98-2-007
Recreational Fish Enhancement
This project continues to provide funds for future rearing opportunities focused on recreation fishing in Puget Sound waters. Specific work will include development of freshwater acclimation ponds in Puget Sound and Hood Canal.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
150,000 71,600 1,078,400 1,000,000 4,000,000 6,300,000
Phase Start Date / End Date Phase Cost
Design 09-01-97 / 04-30-99 85,000
Construction 05-01-98 / 06-30-99 915,000
Funds: Recreational Fisheries Enhancement - State 6,300,000
98-2-008
Mitigation Projects
This project authorizes land acquisition, facility, and infrastructure improvements, and production and habitat development necessary to mitigate for dam construction and habitat damage.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,558,547 2,047,935 1,239,367 6,550,000 26,260,000 38,655,849
Phase Start Date / End Date Phase Cost
Design 11-01-97 / 02-28-99 550,000
Construction 04-01-98 / 06-30-99 6,000,000
Funds: General Fund - Federal 21,593,302
General Fund - Private/Local 12,797,000
Wildlife Account - Federal 500,000
Wildlife Account - Private/Local 1,230,000
Game Special Wildlife Account - Private/Local 2,125,547
Game Special Wildlife Account - State 410,000
98-2-009
Migratory Waterfowl Habitat Acquisition/Development
This project provides funds to acquire threatened waterfowl habitat, enhance wildlife areas and fund projects on private lands to further maintain and enhance waterfowl habitat. Funding is provided through revenues from the Washington Migratory Waterfowl Stamp Program.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,299,300 248,433 251,567 500,000 2,000,000 4,299,300
Phase Start Date / End Date Phase Cost
Design 01-01-97 / 03-31-99 42,500
Construction 07-01-98 / 06-30-99 457,500
Funds: Wildlife Account - State 4,299,300
98-2-010
Columbia River Wildlife Mitigation
This request provides appropriation authority from federal sources to implement wildlife mitigation with the Bonneville Power Administration to offset wildlife losses resulting from six hydropower dams in the Columbia Basin. This will implement wildlife mitigation projects pursuant to the Washington Wildlife Mitigation Agreement with the Bonneville Power Administration and the Northwest Power Planning Council's Fish and Wildlife Program.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
6,600,000 23,200,000 29,800,000
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 12-31-98 127,500
Construction 05-01-98 / 06-30-99 1,572,500
Other 02-01-99 / 06-30-99 4,900,000
Funds: Game Special Wildlife Account - Federal 29,800,000
98-2-012
Fish Passage and Habitat Improvement
This project provides additional federal funding to clear stream blockages and improve fish passage.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
500,000 700,000 1,200,000
Phase Start Date / End Date Phase Cost
Design 09-01-97 / 04-30-99 50,000
Construction 02-01-98 / 06-30-99 450,000
Funds: General Fund - Federal 1,200,000
98-2-013
Deep Water Slough Restoration
This project reforms dike areas to restore the normal flow in Deep Water Slough at the Skagit Wildlife Area to resolve flood flow concerns.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
800,000 2,400,000 3,200,000
Phase Start Date / End Date Phase Cost
Design 09-01-97 / 06-30-98 100,000
Construction 07-01-97 / 06-30-99 700,000
Funds: General Fund - Federal 800,000
General Fund - Private/Local 600,000
State Building Construction Account - State 1,800,000
98-2-019
Clam & Oyster Beach Enhancement
The project will create artifical beds from layers of gravel and shell, and clam and oyster seed. This will provide beds for the increased recreational demand caused by loss of opportunity on natural beds. Additionally, this project will provide a hatchery to produce clam seed.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,711,200 273,747 622,416 300,000 1,600,000 5,507,363
Phase Start Date / End Date Phase Cost
Design 11-30-97 / 04-30-99 25,500
Construction 02-01-98 / 06-30-99 374,500
Funds: Aquatic Lands Enhancement Account - State 2,399,999
State Building Construction Account - State 3,107,364
98-2-020
Replace Unproductive Habitat
This project authorizes the sale and replacement of surplus or upland wildlife habitat lands that have diminished wildlife value.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,600,000 1,600,000
Phase Start Date / End Date Phase Cost
Other 01-01-98 / 06-30-98 1,600,000
Funds: Wildlife Account - State 1,600,000