Central Washington University (CWU) was established in 1890 and is one of the three regional institutions offering baccalaureate and graduate degrees. At present, CWU serves about 7,300 students at its Ellensburg campus. A total of over 50 buildings support instructional, administrative, student and public service, and support functions of the institution. Nearly 30 residence buildings house students on campus. The buildings range in age from nearly new to 100 years old.

Statewide enrollment projections indicate a need to provide additional student access to higher education facilities. While the University's classroom capacity is adequate for such an increase, both laboratory and office space will need significant renovation and renewal over the decade. Five major buildings housing lab-intensive instruction and are now between 20 and 30 years old.


Capital Plan Highlights



1997-99 Agency Detail
Central Washington University
94-2-002
Science Facility
This project funds remedial action for removal and disposal of contaminated soil discovered during the constrcution of the Science Facility.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,650,261 7,502,189 49,047,550 510,000 58,710,000
Phase Start Date / End Date Phase Cost
PreDesign 01-15-92 / 06-05-93 300,000
Design 06-15-93 / 10-15-94 4,300,000
Construction 11-01-94 / 01-15-98 53,600,405
Other 07-01-97 / 06-30-98 510,000
Funds: State Building Construction Account - State 54,200,000
Central Washington University Capital Projects Account - State 4,000,000
Local Toxics Control Account - State 510,000
98-1-020
Chilled Water Systems - Improvements
This project expands the chilled water distribution system, converts distribution pumping system to variable volume, and converts the chillers to a non-ozone refrigerant.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,770,000 1,770,000
Phase Start Date / End Date Phase Cost
Design 10-10-97 / 06-10-98 118,601
Construction 08-10-98 / 06-05-99 1,651,399
Funds: State Building Construction Account - State 1,770,000
98-1-030
Boiler Plant - Expansion
This project expands the boiler plant to meet projected campus heating requirements. This project also includes replacement of deteriorated exterior siding on the existing boiler house.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,450,000 1,450,000
Phase Start Date / End Date Phase Cost
Design 09-10-97 / 05-10-98 129,160
Construction 06-10-98 / 06-10-99 1,320,840
Funds: State Building Construction Account - State 1,450,000
98-1-110
Electrical Utility - Upgrades
This project converts 50 percent of campus medium voltage distribution from 5 KV to 15 KV system, replaces existing 5 KV building transformers, upgrades and expands the substation to accommodate higher voltage and increased electrical loads from the Science Facility and Black Hall remodeling projects. The project will includes Student Village and Brooklane Village on the campus electrical grid, and install new duct bank, vaults and cabling to connect the new 15 KV circuits.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,500,000 4,600,000 7,100,000
Funds: State Building Construction Account - State 7,100,000
98-1-120
Steamline Replacement
This project is an on-going phased project to replace approximately 1600 feet of direct buried steamline with insulated steam piping in a covered concrete trench system.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,450,000 6,320,000 7,770,000
Funds: State Building Construction Account - State 5,660,000
Central Washington University Capital Projects Account - State 2,110,000
98-1-130
Minor Works - Preservation
This project includes small capital modifications and improvements to buildings and other support facilities to maintain their suitability for programs and operations.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,600,000 14,100,000 16,700,000
Funds: Central Washington University Capital Projects Account - State 16,700,000
98-1-170
Building Indoor Air Quality - Improvements
This project will modify building heating, ventilating, and air conditioning equipment and ductwork in 18 academic buildings to improve indoor air quality.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
429,000 2,000,000 2,429,000
Phase Start Date / End Date Phase Cost
Design 09-10-97 / 05-10-98 84,500
Construction 06-10-98 / 06-10-99 642,500
Funds: State Building Construction Account - State
Central Washington University Capital Projects Account - State 2,429,000
98-2-010
SeaTac Center Building - Renovation
This project includes the renovation of a third existing building for occupancy by making code compliance upgrades and modifications for programs.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
662,500 662,500
Phase Start Date / End Date Phase Cost
Design 07-01-97 / 06-30-98 58,410
Construction 07-01-98 / 06-30-99 604,090
Funds: State Building Construction Account - State 662,500
98-2-080
Lynnwood Extended Degree Center - Acquisition
This project will establish a permanent facility for use by the Lynnwood Center.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
1,000,000 4,000,000 5,000,000
Funds: State Building Construction Account - State 5,000,000
98-2-090
Extended Degree Centers
This project includes long-term planning and predesign to define the most cost effective and program supportive facilities and locations for extended degree centers now located in the cities of SeaTac and Yakima.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
150,000 2,000,000 2,150,000
Phase Start Date / End Date Phase Cost
PreDesign 07-01-97 / 06-30-98 150,000
Funds: State Building Construction Account - State 2,000,000
Central Washington University Capital Projects Account - State 150,000
98-2-135
Minor Works - Program
This project includes capital modifications and improvements to buildings and facilities required to support academic and support activities.
.
Prior Biennium Current Biennium Reappropriations Appropriations Future Cost Total Cost
2,000,000 11,200,000 13,200,000